Routine maintenance and spare parts recommendations for D series purge system products
Each quarter:
● Check whether the filter element and oil-water separator need to be replaced. Depending on the condition of the filter element, decide whether the next inspection time
should be advanced to every month or postponed to half a year or one year;
Every 1 year:
● Check whether the low voltage alarm point is normal;
● Whether the pressure holding function is normal;
● Whether there is leakage in the external pipeline connection;
Every 3~5 years:
● Replace the battery;
● Whether the gland and joints are loose;
● Whether the purge time changes;
● Whether the pressure gauge functions normally;
● Check whether the sensor accuracy has changed significantly and whether it needs to be adjusted;
● Check whether the safety valve of the pressure relief unit is opened normally and whether there is a large deviation in the opening pressure;
● Whether each signal output contact can output signals normally and whether the interlocking function is normal.
Recommendations for spare parts for positive pressure cabinet purging equipment
Every half year:
● Check whether the pressure balance hole of the embedded device is blocked;
Every year:
● Check whether the low pressure sensor is functioning properly
● Check whether the flow sensor is operating normally
● Check whether the remote transmission signal is output normally
● Check whether the battery is normal
Every three years:
● Check whether the low pressure sensor value is normal
● Check whether the flow sensor value is normal
● Check whether the red and green flipping balls flip normally
● Check whether the timing module is timing normally
● Check whether the pressure holding value of the pressure relief unit is normal.
● Replace the battery
- Products
- Motor Purge Systems
- Enclosure Purge Systems
- Hazardous area label printers
- Room Pressurization Systems
- Nitrogen Buffer Systems
- EPS Environmental Protection System
- Accessory
- Enclosure Purge Systems
- Projects
- Motor Purging System
- Enclosure purge system
- Room Pressurization Systems
- Nitrogen Buffer Systems
- Ex p Solution for Robot Arm
- Accessory
- News
- Celebrating the 70th anniversary of EXPO - Asia Pacific Celebration and product knowledge training was held in Qingdao
- Friendly Reminders and Required Compliance
- Comer Mechanical and Electrical 2024 Yangzhou group construction tour
- EXITING THE EUROPEAN UNION SANCTIONS
- Bribery Act 2010 2010 CHAPTER 23